A key activity in closing out a project is to
(47)
.
A、
Disseminate status reports and risk assessment.
B、
Disseminate information to formalize project completion.
C、
Monitor the specific project results to determine if they comply with relevant quality standards.
D、
Transfer all the project records to the project owners.
【正确答案】
B
【答案解析】
[分析] 项目收尾时的一个关键活动是发布消息以正式确认项目完工。