单选题 Once the durations of the activities are calculated for a completed network, a forward pass and a backward pass will provide ______.
A) the float of the activities
B) the early start and late start only
C) the critical path
D) A and C

【正确答案】 D
【答案解析】顺推法和逆推法是关键路径CPM中的分析方法。
一旦以整个网络计算活动的时间,顺推法和递推法将提供______。
A) 活动的时差
B) 仅仅是最早开始和最后开始
C) 主要路径
D) A和C