背景 已知某工程的网络计划中相关资料如下表所示。
问答题 根据上表中相关资料绘制网络图;
【正确答案】正确答案:绘制网络图如下:
【答案解析】
问答题 计算总工期,以及网络图中各工作的六个时间参数(ES、EF、LS、LF、TF、FF);
【正确答案】正确答案:计算各工作时间参数: 总工期T=55。 1)计算各工作的ES、EF: ES A =0,EF A =22; ES B —0,EF B =10; ES E =0,EF E =15; ES C =15,EF C =28; ES F =15,EF F =32; ES G =15,EF G =30; ES H =32,EF H =38; ES I =32,EF I =43; ES K =32,EF K =52; ES D =38,EF D =46; ES J =43,EF J =55。 2)计算各工作的LS、LF: LF J =55,LS J =43; LF D =55,LS D =47; LF K =55,LS K =35; LF I =43,LS I =32; LF H =43,LS H =37; LF G =32,LS G =17; LF F =32,LS F =15; LF C =43,LS C =30; LF E =15,LS E =0; LF B =15,LS B =5; LF A =43,LS A =21。 3)计算各工作的TF、FF: TF A =LS A —ES A =21—0=21,FF A =min(ES J ,ES D )一EF A =38—22=16; TF B =LS B —ES B =5一0=5,FF B =min(ES C ,ES F )一EF B =15—10=5; TF C =LS C —ES C =30一15=15,FF C =min(ES J ,ES D )一EF C =38—28=10; TF D =LS D —ES D =47—38=9,FF D =T一EF D =55—46=9; TF E =LS E —ESE=0—0=0,FF E =min(ES C ,ES F ,ES G )一EF E =15—15=0; TF F =LS F 一ES F =15—15=0,FF E =min(ES H ,ES I ,ES K )一EF F =32—32=0; TF G =LS G —ES G =17—15=2,FF G =min(ES H ,ES I ,ES K )一EF G =32—30=2; TF H =LS H —ES H =37—32—5,FF H =min(ES J ,ES D )一EF H =38—38=0; TF I =LS I —ES I =32—32=0,FF I =ES J —EF I =43—43=0; TF J =LS J —ES J =43—43=0,FF I =T一EF J =55—55=0; TF K =LS K —ES J =35—32=3,FF K =T—EF K =55—52=3。
【答案解析】
问答题 找出关键线路,并在图中用双箭线标明。
【正确答案】正确答案:关键线路:E→F→I→J(或①→②→③→④→⑥→⑦)。
【答案解析】