单选题
Charles is working on a project and finds that one of his primary
vendors is raising their costs for a key component of the product being produced
by his project. In order to cover these costs, he ______.
- A. will ask management for a budget increase to cover the difference
- B. will assume management reserve will cover the difference because this
increase was out of his control
- C. will use the cost change control process to obtain approval to use part
of the contingency allowance
- D. will go over budget and ask for forgiveness at the end of the
project