单选题
On a critical project, with a short timeframe, a contractor found an
omission in a proposal which had been submitted and approved. The contractor
indicated this omission may change both scope and thus cost to the project. Upon
receiving notification, the PM should ______.
- A. submit, or ask the vender to submit, a change request to include the
omission in the scope of the project
- B. check the type of the contract used and approve the increase to the
budget
- C. since the project is falling behind, approve both the change in scope and
the additional cost to the project to make sure the project is not delayed
- D. gather more information