单选题
Controling cost can be best described by which of the following?
A. The process of developing the future trends along with the assessment of
probabilities, uncertainties, and inflation that could occur during the
project.
B. The process of assembling and predicting costs of a project over its life
cycle.
C. The process of establishing budgets, standards, and a monitoring system
by which the investment cost of the project can be measured and managed.
D. The process of gathering, accumulating, analyzing, monitoring, reporting,
and managing the costs on an on-going basis;
【正确答案】
D
【答案解析】控制成本的最佳解释是下列哪一项?
A) 是一个未来趋势的完成过程,这个过程包括项目期间对概率、不确定性和通货膨胀的评估。
B) 项目期间项目成本汇总和预测的过程。
C) 是一个确定预算,标准和监控系统的过程,通过该系统可以管理监测项目成本投入。
D) 是一个随时收集、积蓄、分析、监控、报告和管理成本的过程。