单选题
During the execution phase of the project, you realized the
subcontractors are working with incomplete and different scope statements.
As the project manager, what should you do FIRST?
- A. Check the work completed against the correct scope statements.
- B. Review the scope of work with the stakeholders.
- C. Document the inconsistencies to management, calculating the cost of
nonconformance.
- D. Stop all activities until the scope of the work complete.