Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( ).
A、
fast tracking
B、
what-if scenario analysis
C、
resource leveling
D、
critical chain method
【正确答案】
A
【答案解析】