单选题
Which of the following are the most commonly used performance measures of evaluating whether or not work is being accomplished as planned at any given point of time?
【正确答案】
B
【答案解析】[解析] 下列哪项常用来衡量项目的工作是否在特定时间点按原计划完成?
A) PV和AC。 B) AC,EV和PV。
C) CV和SV。 D) SPI,EV和AC。
通过EV、PV和AC这三个数值可以计算CV、SV。