单选题
A project manager is assigned to a new, high priority project. There
are only five available resources because other resources are already committed
to projects. The resource's time available to complete the project is less than
half the time needed, and the project manager cannot convince management to
change the end date. The project manager should ______.
- A. coordinate with team members the overtime necessary to complete the
work
- B. provide the team with opportunities to do a great job on the work that
can be accomplished
- C. cut the scope of work by removing the work that cannot be completed in
the time provided
- D. use more experienced resources to complete the work faster