背景: 已知某工程的网络计划中相关资料如下表所示。
问答题 根据上表绘制网络计划图。
【正确答案】正确答案:绘制网络计划图如下所示:
【答案解析】
问答题 计算总工期,以及网络图中各工作的六个时间参数(ES、EF、LS、LF、TF、FF)。
【正确答案】正确答案:计算总工期:T=15+17+11+12=55。 (1)计算各工作的ES、EF: ES A =0,EF A =22; ES B =0,EF B =10; ES E =0,EF E =15; ES C =15,EF C =28; ES G =15,EF F =32; ES G =15,EF G =30; ES H =32,EF H =38; ESI=32,EFI=43; ES K =32,EF K =52; ES D =38,EF D =46; ES J =43,EF J =55。 (2)计算各工作的LS、LF: LF J =55,LS J =43; LF D =55,LS D =47; LF K =55,LSK=35; LF I =43,LS I =32; LF H =43,LS H =37; LF G =32,LS G =17; LF F =32,LS F =15; LF C =43,LS C =30; LF E =15,LS E =0; LF B =15,LS B =5; LF A =43,LS A =21。 (3)计算各工作的TF、FF: TF A =LS A —ES A =21—0=21,FF A =min(ES J ,ES D )一EF A =38—22=16; TF B =LS B —ES B =5一0=5,FF B =min(ES C ,ES F )一EF B =15—10=5; TF C =LS C —ES C =30—15=15,FF C =min(ES J ,ES D )一EF C =38—28=10; TF D =LS D —ES D =47—38=9,FF D =T—EF D =55—46=9; TF E =LS E —ES E =0—0=0,FF E =min(ES C ,ES F ,ES G )一EF E =15—15=0; TF F =LS F —ES F =15—15=0,FF F =min(ES F ,ES I ,ES K )一EF F =32—32=0; TF G =LS G —ES G =17—15=2,FF G =min(ES H ,ES I ,ES K )一EF G =32—30=2; TF H =LS H —ES H =37—32=5,FF H =min(ES J ,ES D )一EF H =38—38=0; TF I =LS I —ES I =32—32=0,FF I =ES J —EF I =43—43=0; TF J =LS J —ES J =43—43=0,FF J =T—EF J =55—55=0; TF K =LS K —ES K =35一32=3,FF K =T一EF K =55—52=3。
【答案解析】
问答题 写出关键线路(工作表示或节点表示)。
【正确答案】正确答案:工作表示的关键线路:E→F→I→J。 节点表示的关键线路:①→②→③→④→⑥→⑦。
【答案解析】