单选题 Reserve funds are set aside for use when ______.
  • A. an up-scope of the project requires additional funds to compensate the initial budget
  • B. they are needed for the sporadic fluctuation in potential labor rates when a union contract is under negotiation
  • C. anticipated problems have been identified but not completely expected
  • D. a fund used when the client requests an up-score for the project
【正确答案】 C
【答案解析】在什么情况下使用储备金______。 A) 需要添加额外资金以弥补初始预算 B) 当协商劳动合同时,潜在劳动力价格会发生波动 C) 确定发生了预计的问题但没有估计完全 D) 当客户要求项目范围扩展时