单选题
______ is a method of constructing a project schedule
network diagram that uses boxes or rectangles, referred to as nodes, to
represent activites and connects them with arrows that asow the
dependencies. This method includes following types of
dependcies orprecedence relationships: ______, the initiation
of the successor activity, depends upon the completion of the predecessor
activity.
单选题
A. PDM
B. CPM
C. PERT
D. AOA
【正确答案】
A
【答案解析】
单选题
A. F-S
B. F-F
C. S-F
D. S-S
【正确答案】
A
【答案解析】
单选题
______ was developed to make clear the interdependence between project
tasks before those tasks are scheduled.
A. Network Diagram
B. CPM
C. Gantt chart
D. PERT
【正确答案】
D
【答案解析】
单选题
Estimating activity durations uses information on activity scope of
______, required resource types, estimated resource quantities, and resource
calendars.
A. milestone
B. work
C. quality
D. baseline
【正确答案】
B
【答案解析】
单选题
The process of ______ schedule activity durations uses information on
schedule activity scope of work, required resource types, estimated resource
quantities, and resource calendars with resource availabilities.
A. defining
B. estimating
C. planning
D. sequencing
【正确答案】
B
【答案解析】
单选题
Developing the project schedule is often an iterative process. It
determines the planned start and finish dates for project activities and
milestones. Schedule development can require the review and revision of duration
estimates and resource estimates to create an approved project schedule that can
serve as a baseline to ______ progress.
A. analyze
B. track
C. level
D. extend
【正确答案】
B
【答案解析】
单选题
Many useful tools and techniques are used in developing schedule.
______ is a schedule network analysis technique that modifies the project
schedule to account for limited resource.
A. PERT
B. Resource leveling
C. Schedule compression
D. Critical chain method
【正确答案】
D
【答案解析】
单选题
Project schedule management is made up of six management processes
including: activity definition, activity sequencing, ______, and schedule
control by order.
A. activity duration estimating, schedule developing, activity resource
estimating
B. activity resource estimating, activity duration estimating, schedule
development
C. schedule developing, activity resource estimating, activity duration
estimating
D. activity resource estimating, schedule developing, activity duration
estimating
【正确答案】
B
【答案解析】
单选题
On some projects, especially ones of smaller scope, activity
sequencing, activity resource estimating. Activity duration estimating, and
______ are so tightly linked that they are viewed as a single process that can
be performed by a person over a relatively short period of time.