单选题 Project team A has been hired to manage a transportation project very similar to dozens at projects they've managed successfully in the past.The team had determined that the probability of achieving project objectives is 94%.The team has determined the size of contingency reserves that may be needed.These determinations are included in which process?
【正确答案】 C
【答案解析】[解析] 项目小组A受雇管理一个运输项目,该项目与他们以前成功管理过的许多项目相似。该小组确定达成该项目目标的可能性是94%。小组还确定了可能需要的应急储备的范围。这些判断包括在下列哪一程序中? A) 定性的风险分析。 B) 风险应对计划。 C) 定量的风险分析。 D) 风险标识。 本题描述情况为风险定量分析过程的输出______风险登记册(更新)中的内容(项目成功概率、应急储备范围)。