单选题 Project sequencing is best described as: A. prioritizing funds to achieve the maximum value for shareholders, given capital limitations. B. selecting the first project from a set of mutually exclusive projects. C. an investment in a project today that creates the opportunity to invest in other projects in the future.
【正确答案】 C
【答案解析】Projects are often sequenced through time so that investing in a project today may create the opportunity to invest in other projects in the future. Note that funding from the first project is not a requirement for project sequencing.