选择题 75.  In a project plan, when the project manager schedules activities, he (or she) often uses ______ method, precedence relationships between activities are represented by circles connected by one or more arrows. The length of the arrow represents the duration of the relevant activity.
【正确答案】 D
【答案解析】 在项目计划中,当项目经理安排活动时,他(或她)经常使用箭线图方法,活动之间的优先级关系用一个或多个箭头连接的圆来表示。箭头的长度代表相关活动的持续时间。