JME Construction always uses the percentage of completion method of
recognizing revenue. During 2004 JME signs a contract in the amount of $10
million with the following data available:
Costs incurred to date |
$2200000 |
Billings to date |
$2000000 |
Cash collected |
$1750000 |
Total cost of project |
$8800000 |
How much gross
profit should JME recognize for 2004?
- A. $ 300000.
- B. $450000.
- C. $ 200000.