单选题 Which of the following is not part of a modern quality management concept? ______
A. Performance standard is zero defects
B. Quality must be inspected in
C. 85% of failures occur because of the process, not the worker
D. Quality is a 4 cycle process - plan/do/check/act

【正确答案】 B
【答案解析】