单选题
The most crucial time for project risk assessment is______. A. when a problem surfaces B. during the planning phase C. during the close-out phase D. after the project schedule has been published
【正确答案】
B
【答案解析】[解析] 进行项目风险评估最关键的时候是:规划阶段(during the planning phase)。 选项A:问题出现时。选项C:结束阶段。选项D:项目进度公布之后。