(2009年下半年)(73)is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activities and connects them with arrows that show the logical relationships that exist between them.
【正确答案】 D
【答案解析】解析:(73)是一种在关键路径法中用来编制项目进度网络图的方法,它用盒子或矩形(称为节点)来代表活动,并将节点用箭头连接起来,以表达节点之间的逻辑关系。