单选题 The method of constructing a project schedule network diagram that represents activities and connects then to show the all dependencies is known as______.
A) precedence diagramming method B) activity list
C) arrow diagramming method D) schedule network templates

【正确答案】 A
【答案解析】[解析] ______能够展示所有活动的依赖关系。
A) PDM(前导图) B) 活动列表 C) ADM(箭线图) D) 进度网络模板