单选题
The customer asks your project to be completed 6 months earlier than planned.You think this target can be reached by-overlapping project activities. This approach is known as ().
A、
balance engjneering
B、
fast-tracking
C、
leveling
D、
crashing
【正确答案】
B
【答案解析】