单选题

In a project plan, when the project manager schedules activities, he (or she) often uses (     ) method,precedence relationships between acticities are represented by cireles connected by one or more arrows. The length of the arrow represents the duration of the relevant activity. 

【正确答案】 D
【答案解析】