Estimate activity duration is the process of estimating the number of work periods to complete activities with estimated resources .The tools and technique is not including. ______
A、
expert judgment
B、
analogous estimating
C、
requirements traceability matrix
D、
three-point estimating
【正确答案】
C
【答案解析】