单选题
Based on quality control measurements on your manufacturing project,
management releases that immediate corrective action is required to the material
requirements planning (MRP) system to prevent future problems on other projects
and to minimize rework. To implement the necessary changes you should follow
______.
- A. the organization's quality policy
- B. the quality management plan
- C. established operational definitions and procedures
- D. procedures for integrated change control