单选题
Changes may be requested by any stakeholder involved with the project, but changes can be author5zed only by ______.
A.executive IT manager
B.project manger
C.change control board
D.project sponsor
A
B
C
D
【正确答案】
C
【答案解析】
[解析] 变更可以被任何项目干系人发起,但变更只能被CCB(Change Control Board,变更控制委员会)授权批准。