【答案解析】FF
D
=min{ESG}-EF
D
=ESG-EF
D
=20-20=0
TF
D
=LS
D
-ES
D
=LF
D
-D-ES
D
=LF
D
-7-13=45-10-11-20=4
FF
E
=min{ES
H
}-EF
E
=ES
H
-EF
E
=28-22=6
TF
E
=LS
E
-ES
E
=LF
E
-E-ES
E
=LF
E
-9-13=45-10-7-9-13=6
FF
G
=min{ES
J
}-EF
G
=ES
J
-EF
G
=45-10-31=4
TF
G
=LS
G
-ES
G
=LF
G
-11-20=45-10-11-20=4
[解析] 从活动A开始能到活动G的只有一条路,即ABDG,最快的情况就是这条路一点都不延误,故ESG=A+B+D=20。
同理EF
D
=A+B+D=20。
FF
D
=min{ES
G
}-EF
D
=ES
G
-EF
D
=20-20=0
TF
D
=LS
D
-ES
D
=LF
D
-D-ES
D
=LF
D
-7-13=45-10-11-7.13=4
总工期是45,可从后往前推,D在唯一路ABDGJ上,故LF
D
=总工期-J-G=45-10-11=24
FF
E
=min{ES
H
}-EF
E
=ES
H
=EF
E
=28-22=6
H在关键路径上,不允许延误,故ES
H
=A+C+F+I=28。经过E只有唯一的一条路,那就是ABE,故EF
E
=A+B+E=22
TF
E
=LS
E
-ES
E
=LF
E
-E-ES
E
=LF
E
-9-13=LF
E
-22=45-10-7-22=45-39=6
求LF
E
时,考虑到E在唯一的路上,即ABEHJ,总工期为45,故E最晚完成的时间是:总工期-J-H=45-10-7=28。
FF
G
=min{ES
J
}-EF
G
=ES
J
-EF
G
=45-10-31=4
TF
G
=LS
G
-ES
G
=LF
G
-11-20=45-10-11-20=4