单选题 The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to ______.
A. measure, delay, record, distribute, analyze, and direct
B. plan, schedule, monitor, control, report, and forecast
C. promote, highlight, monitor, control, forecast, and report
D. emphasize, visualize, analyze, conceptualize, report, and record

【正确答案】 B
【答案解析】[参考译文] 项目进度计划是规定在一段时间内相关活动的多文档,它代表该项目的时间维度,是一种用于决策的管理工具。因此项目管理团队可用它进行准备(plan)、议程(schedule)、监测(monitor)、控制(control)、报告(report)和预测(forecast)。