工作 |
紧后工作 |
持续时间(天) |
可压缩时间 |
工序费用(万元) |
压缩单位时间增加费用(万元/天) |
A |
C,D,E,F |
12 |
2 |
18 |
2 |
B |
D,E,F |
26 |
2 |
40 |
4 |
C |
G,H |
24 |
2 |
25 |
3.5 |
D |
G,H |
6 |
0 |
15 |
1 |
E |
I,K |
12 |
1 |
40 |
2 |
F |
K,J |
40 |
5 |
120 |
2 |
G |
I,K |
8 |
1 |
16 |
2 |
H |
J |
28 |
2 |
37 |
1.5 |
I |
J |
4 |
0 |
10 |
1 |
J |
— |
32 |
2 |
64 |
6 |
K |
— |
16 |
2 |
16 |
2 |