单选题 Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.
A.Develop Schedule B.Estimate Activity Resources
C.Define Activities D.Sequence Activities

【正确答案】 A
【答案解析】项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。