单选题
A project life cycle is a collection of generally
sequential project ______ whose name and number are determined by the control
needs of the organization or organizations involved in the project. The life
cycle provides the basic ______ for managing the project, regardless of the
specific work involveD.
单选题
A. phases
B. processes
C. segments
D. pieces
【正确答案】
A
【答案解析】
单选题
A. plan
B. fraction
C. main
D. framework
【正确答案】
D
【答案解析】
单选题
The project life-cycle can be described as______.
A. project concept, project planning, project execution, and project
close-out
B. project planning, work authorization, and project reporting
C. project planning, project control, project definition, WBS development,
and project termination
D. project concept, project execution, and project reporting
【正确答案】
A
【答案解析】
单选题
The ______ defines the phases that connect the beginning of a project
to its enD.
A. milestone
B. schedule
C. temporary
D. project life cycle
【正确答案】
D
【答案解析】
单选题
The project maintains a current and approved set of requirements over
the life of the project by doing the following: ______ all changes to the
requirements Maintaining the relationships among
the requirements, the project plans, and the work products. …
A. Monitoring
B. Managing
C. Gathering
D. Reducing
【正确答案】
B
【答案解析】
单选题
______ means that every project has a definite beginning and a definite
end.
A. Project phase
B. Unique
C. Closure
D. Temporary
【正确答案】
D
【答案解析】
单选题
______ from one phase are usually reviewed for completeness and
accuracy and approved before work starts on the next phase.
A. Deliverables
B. Milestone
C. Work
D. Process
【正确答案】
A
【答案解析】
单选题
______ is ameasurable, verifiable work poduct such as specification
feasibility study report, detail document, or working prototype.
A. Deliverable
B. Project charter
C. Earned value
D. Milestone
【正确答案】
A
【答案解析】
单选题
______ are individuals and organizations that are actively involved in
the project, or whose interests may be affected as aresult of project execution
or project completion; they may also exert influence over the project and its
results.
A. controls
B. baselines
C. project managers
D. project stakeholders
【正确答案】
D
【答案解析】
单选题
The ______ Process Group consists of the processes used to complete
the work defined in the project management plan to accomplish the project's
requirements.
A. Planning
B. Executing
C. Monitoring and Controlling
D. Closing
【正确答案】
B
【答案解析】
单选题
Organizations perform work to achieve a set of objectives. Generally,
work can becategorized as either projects or operations, although the two
sometimes are ______.
A. confused
B. same
C. ovedap
D. dissever
【正确答案】
C
【答案解析】
单选题
The inputs of developing project management plan do not include
______.
A. project charter
B. stakeholder management strategy
C. project scope statement
D. outputs from planning processes
【正确答案】
B
【答案解析】
单选题
The Develop Project Management Plan Process includes the actions
necessary to define, prepare, integrate, and coordinate all constituent plans
into a ______.
A. Project Scope Statement
B. Project Management Plan
C. Forecasts
D. Project Charter
【正确答案】
B
【答案解析】
单选题
All of followings should be done by the project manager during project
control except ______
A. Determine the a change has occurred
B. Ensure that a change is agreed
C. Make sure all changes are approved by management
D. Manage changes as they occur
【正确答案】
C
【答案解析】
单选题
The ______ provides the project manager with the authority to apply
organizational resources to project activities.
A. project management plan
B. project charter
C. project human resource plan
D. project stakeholders
【正确答案】
B
【答案解析】
单选题
Most system development methodologies also provide ______, whose
purpose is to contain the various pieces of relevant information-feasibility
assessments, schedules, needs analysis, and so forth-in a single place so that
they can be presented to project clients and other related parties.
A. statement of work
B. project planning
C. baseline plan
D. information system planning
【正确答案】
C
【答案解析】
单选题
Changes may be requested by any stakeholder involved with the project,
but changes can be authorized only by ______.
A. executive IT manager
B. project manger
C. change control board
D. project sponsor
【正确答案】
C
【答案解析】
单选题
In the project management context, ______ includes characteristics of
unification, consolidation, articulation, and integrative actions that are
crucial to project completion, successfully meeting customer and other
stakeholder requirements, and managing expectations.
A. integration
B. scope
C. process
D. charter
【正确答案】
A
【答案解析】
单选题
______ is primarily concerned with defining and controlling what is
and is not included in the project.
A. Project Time Management
B. Project Cost Management
C. Project Scope management
D. Project Communications Management
【正确答案】
C
【答案解析】
单选题
A project manager believes that modifying the scope of the project may
provide added value service for the customer. The project manager should ______.
A. assign change tasks to project members
B. call a meeting of the configuration control board
C. change the scope baseline
D. postpone the modification until a separate enhancement project is funded
after this project is completed according to the original baseline
【正确答案】
D
【答案解析】
单选题
Which of the following Project Scope Management processes involves
subdividing the major project deliverables into smaller, more manageable
components? ______.
A. Scope Planning
B. Scope Verification
C. Scope Change Control
D. Scope Definition
【正确答案】
D
【答案解析】
单选题
The work breakdown structure comprises several levels of decomposition
of the total project. The lowest level of definition is always the ______.
A. planning element
B. work package
C. subtask
D. working interface
【正确答案】
B
【答案解析】
单选题
Project manager believes that modifying the project scope may provide
added value for the customer. The project manager should ______.
A. change the scope baseline
B. contact the customer to determine if the change adds value
C. call a meeting of the change control board
D. change the project's objectives
【正确答案】
B
【答案解析】
单选题
______ describes, in detail, the project's deliverables and the work required to create those deliverables.
A. Product scope description B. Project objectives
C. Produce specification D, The project scope statement
【正确答案】
D
【答案解析】
单选题
To ensure the project team provide the functionality the customer expects in a new piece of software, the project manager asks the customer for sign-off on the design criteria. There documents are ______.
A. technical specifications B. performance specifications
C. product descriptions D, quality assurance
【正确答案】
A
【答案解析】
单选题
The work that needs to be accomplished to deliver a product, service,
or result with the specified features and functions is called ______.
A. Scope management
B. Integrated management
C. SOW
D. PMO
【正确答案】
A
【答案解析】
单选题
Which of following is an important input to scope verification?
______.
A. Work results
B. Historical information
C. Formal acceptance
D. Change request
【正确答案】
A
【答案解析】
单选题
Project ______ Management includes the processes required to ensure
that the project includes all the work required, and only the work required, to
complete the project successfully.
A. Integration
B. Configuration
C. Scope
D. Requirement
【正确答案】
C
【答案解析】
单选题
Creating WBS means subdividing the major project deliverables into
smaller components until the deliverables are defined to the ______ level.
A. independent resource
B. individual work load
C. work milestone
D. work package
【正确答案】
D
【答案解析】
单选题
The creation of a work breakdown structure (WBS) is the process of
______ the major project deliverables.
A. subdividing
B. assessing
C. planning
D. integrating
【正确答案】
A
【答案解析】
单选题
A project management technique that is currently in widespread use is
the ______. The purpose of this technique is to detail, in hierarchical fashion,
all of the activities that are required to meet project objectives.
A. Structure Chart
B. Organizational Structure
C. Work Breakdown Structure
D. Functional decomposition diagram
【正确答案】
C
【答案解析】
单选题
______ is the process of obtaining the stakeholdrs' formal acceptance
of the completed project scope. Verifying the scope includes reviewing
deliverables and work results to ensure that all were completed satisfactorily.
A. WBS Creation
B. scope definition
C. project acceptance
D. scope verification
【正确答案】
D
【答案解析】
单选题
______ is a method used in Critical Path Methodology for constructing
a project schedule network diagram that uses boxes or rectangles, referred to as
nodes, to represent activities and connects them with arrows that show the
logical relationships that exist between them.
A. PERT
B. AOA
C. WBS
D. PDM
【正确答案】
D
【答案解析】
单选题
Schedule development can require the review and revision of duration
estimates and resource estimates to create an approved ______ that can serve as
a baseline to track progress.
A. scope statement
B. activity list
C. project charter
D. project schedule
【正确答案】
D
【答案解析】
单选题
The project schedule is more than a document that lays out the
activities over time to represent the time dimension of the project, it is a
management tool to be used for decision making. As such, the schedule is used by
the project management team to ______.
A. measure, delay, record, distribute, analyze, and direct
B. plan, schedule, monitor, control, report, and forecast
C. promote, highlight, monitor, control, forecast, and report
D. emphasize, visualize, analyze, conceptualize, report, and
record
【正确答案】
B
【答案解析】
单选题
______ is not the advantage of GERT (graphical evaluation and review
techniques) as compared with PERT (project evaluation and review techniques).
A. Allowing looping
B. Allowing for dummy tasks
C. Allowing branching
D. Allowing multiple project end results
【正确答案】
A
【答案解析】
单选题
In project management, a ______ is a list of a project's milestones,
activities, and deliverables, usually with intended start and finish dates.
Those items are often estimated in terms of resource allocation, budget and
duration, linked by dependencies and scheduled events.
A. schedule
B. WBS
C. SOW
D. charter
【正确答案】
A
【答案解析】
单选题
Project work packages are typically decomposed into smaller components
called activities to provide a basis for ______, scheduling, executing, and
monitoring and controlling the project work.