单选题 "OH DEAR! Oh dear! I shall be too late!" So muttered the White Rabbit just before he plunged into Wonderland, with Alice in pursuit. Similar utterances have been escaping the lips of European physicists, as it was confirmed last week that their own subterranean Wonderland, a new machine called the Large Hadron Collider, will not now begin work until May 2008. This delay may enable their American rivals to scoop them by finding the Higgs boson—predicted 43 years ago by Peter Higgs of Edinburgh University to be the reason why matter has mass, but not yet actually discovered.
The Large Hadron Collider is a 27km-long circular accelerator that is being bulk at CERN, the European particle-physics laboratory near Geneva, specifically to look for the Higgs boson. When it eventually starts work, it will be the world"s most powerful particle collider. It will also be the most expensive, having cost $ 8 billion to build. The laboratory had hoped it would be ready in 2005, but the schedule has slipped repeatedly.
The most recent delay came at the end of March, with the dramatic failure of a magnet assembly that had been supplied by CERN"s American counterpart, the Fermi National Accelerator Laboratory (Fermi lab) near Chicago. This device was one of four designed to focus beams of particles before they collide in the experimental areas. Admittedly, it had been placed under extreme conditions when it failed, but such forces are to be expected from time to time when the machine is running normally. The magnets have yet to be fixed, although physicists think they know how to do it.
Other, smaller hitches have compounded the problem. The collider has been built in eight sections, each of which must be cooled to temperatures only just above absolute zero. This is because the magnets used to accelerate the particles to the high energies needed for particle physics rely on the phenomenon of superconductivity to work—and superconductivity, in turn, needs extremely low temperatures. Unfortunately, the first of the eight sections took far longer to chill than had been expected.
If, as the other seven sections are cooled, further problems emerge, the start date will have to be put back still further. It takes a month to cool each section, and a month to warm each one back up to normal temperatures again. If it took, say, a month to fix any problems identified as a section cooled, each cycle would postpone the start date by three months.
To accelerate progress (as well as particles), CERN"s management decided last week to cancel an engineering run scheduled for November. Instead of beginning slowly with some safe-but-dull low-energy collisions, the machine"s first run will accelerate its particles to high energies straight away.
Such haste may be wise, for rumours are circulating that physicists working at the Tevatron, which is based at Fermi lab and is currently the world"s most powerful collider, have been seeing hints of the Higgs boson. Finding it would virtually guarantee the discoverer a Nobel prize—shared jointly, no doubt, with Dr. Higgs. Hence the rush, as hundreds of physicists head down the rabbit hole, seeking their own adventures in Wonderland.
单选题 The sentences in Alice in Wonderland are cited in the first paragraph in order to ______.
【正确答案】 C
【答案解析】[解析] 细节考查题。第一段所引用的句子表明是“太晚了”,联系到物理学家要推迟推出新机器,可以看出这只是反映他们推迟了这个项目。
单选题 The word "scoop" (Line 5, Paragraph 1 most probably means ______.
【正确答案】 A
【答案解析】[解析] 猜词题。美国的对手先发现西格斯介子的玻色子,就应该会抢在欧洲人前面。
单选题 Which one of the following statements is TRUE of Peter Higgs" contribution in this field?
【正确答案】 A
【答案解析】[解析] 细节考查题。答案参见第一段最后一句,Peter Higgs只是预言玻色子为什么有质量。
单选题 The schedule of the Large Hadron Collider has slipped repeatedly because of the following reason except ______.
【正确答案】 B
【答案解析】[解析] 细节考查题。文中第三段、第四段和第五段列出了有关计划日程不断推后的原因。
单选题 CERN"s management decided to have the machine"s first run accelerate its particles straight away because ______.
【正确答案】 A
【答案解析】[解析] 细节考查题。第七段表示有传闻说Tevatron工作的物理学家已经看到了西格斯玻色子的迹象,欧洲还是怕美国超前,因此选择了这样的策略。