单选题
Project work packages are typically decomposed into smaller components called activities to provide a basis for
(72)
, scheduling, executing, and monitoring and controlling the project work.
A、
reviewing
B、
estimating
C、
auditing
D、
expecting
【正确答案】
B
【答案解析】
[参考译文] 把项目工作包分解成更小的结构称为活动的单元,为估算、进度安排、项目执行、项目监控提供了基础。