选择题
74.
Earned Value Management(EVM) integrates the scope baseline with the ______ baseline, along with schedule baseline, to form the performance baseline, which helps the project management team assess and measure project performance and progress.
A、
quality
B、
risk
C、
change
D、
cost
【正确答案】
D
【答案解析】