The Better Building Company has a contract to build a building for $100 million. The estimate of the cost of the project is $ 75 million. In the first year of the project, BB had costs of $ 30 million. The Better Building Company' s reported profit for the first year of the contract, using the percentage-of-completion method, is:
【正确答案】
C
【答案解析】Reported profit (in millions) = ($30/$75)×($100-75) = $10.