问答题 背景
已知某工程的网络计划中相关资料如下表所示。
工作 紧前工作 持续时间
A 22
B 10
C B、E 13
D A、C、H 8
E 15
F B、E 17
G E 15
H F、G 6
I F、G 11
J A、C、I、H 12
K F、G 20
问题
问答题 根据上表中相关资料绘制网络图;
【正确答案】
【答案解析】绘制网络图如下:
问答题 计算总工期,以及网络图中各工作的六个时间参数(ES、EF、LS、LF、TF、FF):
【正确答案】
【答案解析】计算各工作时间参数:
总工期T=55。
1)计算各工作的ES、EF:
ES A =0,EF A =22;
ESB=0,EFB=10;
ESE=0,EFE=15;
ES C =15,EF C =28;
ES F =15,EF F =32;
ES G =15,EF G =30;
ES H =32,EF H =38;
ES I =32,EF I =43;
ES K =32,EF K =52;
ES D =38,EF D =46;
ES J =43,EF J =55。
2)计算各工作的LS、LF:
LF J =55,LS J =43;
LF D =55,LS D =47;
LF K =55,LS K =35;
LF I =43,L5 I =32;
LF H =43,LS H =37;
LF G =32,LS G =17;
LF F =32,LS F =15;
LF C =43,LS C =30;
LF E =15,LS E =0;
LF B =15,LS B =5;
LF A =43,LS A =21。
3)计算各工作的TF、FF:
TF A =LS A -ES A -21-0=21,FF A =min(ES J ,ES D -EF A =38-22=16;
TF B =LS B -ES B =5-0=5,FF B =min(ES C ,ES F )-EF B =15-10=5;
TF C =LS C -ES C =30-15-15,FF C =min(ES j ,ES D )-EF C =38-28=10;
TF D =LS D -ES D =47-38=9,FF D =T-EF D =55-46=9;
TF E =LS E -ES E =0-0=0,FF E =min(ES C ,ES F ,ES G )-EF E -15-15=0;
TF F =LS F -ES F =15-15=0,FF E =min(ES H ,ES l ,ES K )-EF F =32-32=0;
TF G =LS G -ES G =17-15=2,FF G =min(ES H ,ES l ,ES K )-EF G =32-30=2;
TF H =LS H -ES H =37-32=5,FF H =min(ES J ,ES D )-EF H =38-38=0;
TF I =LS I -ES I =32-32=0,FF I =ES J -EF I =43-43=0;
TF J =LS J -ES J =43-43=0,FF l =T-EF J -55-55=0;
TF K =LS K -ES K =35-32=3,FF K =T-EF K =55-52=3。
问答题 找出关键线路,并在图中用双箭线标明。
【正确答案】
【答案解析】关键线路:E→F→I→J(或①→②→③→④→⑥→⑦)。