单选题
Two months into a design project, the customer requested a modification
to the project. The change was made a without notify the project manager. During
the final testing phase, result were different from what was planned for, This
scenario is an example of which of following?
- A. Poor definition of the test plan.
- B. Poor development of quality management plan.
- C. Poor use of scope change control.
- D. Poor adherence to the communication plan.