单选题
In the following table, which project is most likely to finish ahead of
schedule?
- A. Project A
- B. Project B
- C. Project C
- D. All three the projects will be completed at the same time
Project |
BCWS |
BCWP |
ACWP |
A B C |
1000 1000 1000 |
800 600 1200 |
600 800 800 |
|