单选题 75.________ involves comparing actual or planned proj ect practices to those of other proj ects to generate ideas for improvement and to provide a basis by which to measure performance.These other projects can be within the performing organization or outside of it,and can be within the same or in another application area.
【正确答案】 C
【答案解析】 试题64讲评:involves表示“涉及”,comparing actual or planned project practices to表示“与什么比较实际的或计划的项目实践”,to generate ideas for improvement表示“用来生成改进的思想、主意”,provide a basis by which to measure performance表示“提供一个测量绩效的基准”。be within the performing organization or outside ofit表示“可以是执行组织内部的,也可以是外部的”,can be within the same or in another application area表示“可以是同一个应用领域的,也可以是其他应用领域”。选项A是“度量标准体系’’,选项B是“测量”,选项C是“基准评价”,选项D是“基线”。根据题意,表示这个术语是供项目内外比较的基准,故选项C最为合适。