单选题 ______ assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.
  • A.Quantitative Risk Analysis
  • B.Qualitative Risk Analysis
  • C.Enterprise Environmental Factors
  • D.Risk Management Plan
【正确答案】 B
【答案解析】[解析] ·定性风险分析(Qualitative Risk Analysis)根据风险发生的可能性、风险发生后对项目目标的相应影响以及其他因素(如应对时间要求,与成本、进度、范围和质量等项目制约因素相关的风险承受力),来评估已识别风险的优先级。 ·A选项是定量风险分析。