背景:已知某工程的网络计划中相关资料如下表所示。
问答题 根据上表绘制网络计划图。
【正确答案】正确答案:绘制网络计划图如下所示:
【答案解析】
问答题 计算总工期,以及网络图中各工作的六个时间参数(ES、EF、LS、LF、TF、FF)。
【正确答案】正确答案:计算总工期:T=15+17+11+12=55。 (1)计算各工作的ES、EF: ES A =0,EF A =22; ES B =0,EF B =10; ES E =0,EF E =15; ES C =15,EF C =28; ES F =15,EF F =32; ES G =15,EF G =30; ES H =32,EF H =38; ES I =32,EF I =43; ES K =32,EF K =52; ES D =38,EF D =46; ES J =43,EF J =55。 (2)计算各工作的LS、LF: LF J =55,LS J =43; LF D =55,LS D =47; LF K =55,LS K =35; LF I =43,LS I =32; LF H =43,LS H =37; LF G =32,LS G =17; LF F =32,LS F =15; LF C =43,LS C =30; LF E =15,LS E =0; LF B =15,LS B =5; LF A =43,LS A =21。 (3)计算各工作的TF、FF: TF A =LS A ﹣ES A =21﹣0=21,FF A =min(ES J ,ES D )﹣EF A =38﹣22=16; TF B =LS B ﹣ES B =5﹣0=5,FF B =min(ES C ,ES F )﹣EF B =15﹣10=5; TF C =LS C ﹣ES C =30﹣15=15,FF C =min(ES J ,ES D )﹣EF C =38﹣28=10; TF D =LS D ﹣ES D =47﹣38=9,FF D =T﹣EF D =55﹣46=9; TF E =LS E ﹣ES E =0﹣0=0,FF E =min(ES C ,ES F ,ES G )﹣EF E =15﹣15=0; TF F =LS F ﹣ES F =15﹣15=0,FF E =min(ES H ,ES I ,ES K )﹣EF F =32﹣32=0; TF G =LS G ﹣ES G =17﹣15=2,FF G =min(ES H ,ES I ,ES K )﹣EF G =32﹣30=2; TF H =LS H ﹣ES H =37﹣32=5,FF H =min(ES J ,ES D )﹣EF H =38﹣38=0; TF I =LS I ﹣ES I =32﹣32=0,FF I =ES J ﹣EF I =43﹣43=0; TF J =LS J ﹣ES J =43﹣43=0,FF J =T﹣EF J =55﹣55=0; TF K =LS K ﹣ES K =35﹣32=3,FF K =T﹣EF K =55﹣52=3。
【答案解析】
问答题 写出关键线路(工作表示或节点表示)。
【正确答案】正确答案:工作表示的关键线路:E→F→I→J。 节点表示的关键线路:①→②→③→④→⑥→⑦。
【答案解析】