单选题 Sunk costs are ______.
  • A. dollars that have not been invested by are in the management reserve
  • B. cost that vary in total depending upon the activity of the project as compared to fixed costs
  • C. another name for labor cost since these costs are already budgeted
  • D. dollars already invested in the project will not affect the project's outcome regardless of what is done
【正确答案】 D
【答案解析】沉淀成本是______。 A) 管理储备中未使用的资金 B) 项目活动和固定成本之间的差别成本 C) 已做预算的人工成本别名 D) 对项目结果不会产生影响的已投入成本