单选题 An analyst does capital budgeting about two independent projects.
Project Net Present Value Internal Rate of Return
1 $150 18%
2 $200 15%
If the investor's required rate of return is 12%, which project should most likely be accepted?
A. Project 1.
B. Project 2.
C. Projectl and Project 2.

【正确答案】 C
【答案解析】[解析] 对于单个项目,根据NPV和IRR会得出相同的决策。对于相互独立项目(independent projects),只要NPV>0,就可以接受该项目;但如果NPV<0,就应该拒绝该项目。对于互斥的项目(mutually exclusive projects),应在NPV>0的项目中选择NPV最大的项目;当IRR与NPV对作决策有冲突时,以NPV为准,因为NPV越大,越能增加股东的权益。