单选题
A team member notifies the project manager that the activities comprising a work package are no longer appropriate.It would be BEST for the project manager to be in what part of the project management process?
【正确答案】
C
【答案解析】[解析] 项目团队成员通知项目经理某些工作包所包含的活动不再合适。项目经理此刻在哪个项目管理过程组内?
A) 纠正行动。 B) 整体变更控制。 C) 监视与控制。 D) 项目收尾。