单选题

A company entered into a three-year construction project with a total contract price of $10.6 million and an expected total cost of $8.8 million. The following table provides cash flow information relating to the contract:

All figures in millions Year 1 Year 2 Year 3
Costs incurred and paid $1.2 $6.0  $1.6
Amounts billed and payments received $2.4  $5.6 $2.6

If the company uses the percentage-of-completion method, the amount of revenue recognized (in millions) in Year 2 is closest to:

【正确答案】 C
【答案解析】

C is correct. The revenue reported is equal to the percentage of the contract that is completed in that period, where percentage completion is based on costs.
In Year 2: (6.0 ÷ 8.8) × 10.6 = 7.2.