单选题 The PM and project team have completed decomposition and have verified scope, when the marketing department makes a minor change to the product functionality to improve its appeal to the end customer. The PM and the project team ______.
  • A. refuses to accept the change since the scope has been veri{ied
  • B. modifies the WBS and the decomposition
  • C. accepts the change and incorporates it into the WBS, modifying the budget and the schedule and assigning accountability to the marketing team
  • D. proceeds per the change process
【正确答案】 D
【答案解析】A变更并不总是有害的,核实范围后的变更是有可能的。B在变更请求得到批准以前,不应修改。C是否接受变更要通过变更程序。D正确。 项目经理和他的团队已经完成了项目分解并确认了范围,这时市场部门为了提高产品对顾客的吸引力而对产品功能做了细微的变更。项目经理和他的团队应该______。 A) 由于范围已被确认因此拒绝变更 B) 修改WBS和项目分解 C) 接受变更并加入WBS,修改预算和进度并把责任指派给市场团队 D) 进行变更程序