单选题
The PM and project team have completed decomposition and have verified
scope, when the marketing department makes a minor change to the product
functionality to improve its appeal to the end customer. The PM and the project
team ______.
- A. refuses to accept the change since the scope has been veri{ied
- B. modifies the WBS and the decomposition
- C. accepts the change and incorporates it into the WBS, modifying the budget
and the schedule and assigning accountability to the marketing team
- D. proceeds per the change process