单选题
The schedule management plan is a component of the project management plan The schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.
A、
goals
B、
values
C、
needs
D、
level
【正确答案】
C
【答案解析】
提交答案