| 表2-3 功能权重计算表 | |||||||
| 功能 | F1 | F2 | F3 | F4 | F5 | 得分 | 权重 |
| F1 | × | 3 | 1 | 3 | 3 | 10 | 0.250 |
| F2 | 1 | × | 0 | 2 | 2 | 5 | 0.125 |
| F3 | 3 | 4 | × | 4 | 4 | 15 | 0.375 |
| F4 | 1 | 2 | 0 | × | 2 | 5 | 0.125 |
| F5 | 1 | 2 | 0 | 2 | × | 5 | 0.125 |
| 合计 | 40 | 1.000 | |||||
| 表2-4 各方案功能指数计算表 | ||||
| 方案功能 | 功能权重 | 方案功能加权得分 | ||
| A | B | C | ||
| F1 | 0.250 | 9×0.250=2.250 | 8×0.250=2.000 | 9×0.250=2.250 |
| F2 | 0.125 | 8×0.125=1.000 | 7×0.125=0.875 | 8×0.125=1.000 |
| F3 | 0.375 | 8×0.375=3.000 | 10×0.375=3.750 | 10×0.375=3.750 |
| F4 | 0.125 | 7×0.125=0.875 | 6×0.125=0.750 | 8×0.125=1.000 |
| F5 | 0.125 | 10×0.125=1.250 | 9×0.125=1.125 | 8×0.125=1.000 |
| 合计 | 8.375 | 8.500 | 9.000 | |
| 功能指数 | 8.375/25.875=0.324 | 8.500/25.875=0.329 | 9.000/25.875=0.348 | |
| 表2-5 各方案价值指数计算表 | ||||
| 方案 | 功能指数 | 单方造价/(元/m2) | 成本指数 | 价值指数 |
| A | 0.324 | 2560 | 0.3360 | 0.9643 |
| B | 0.329 | 2640 | 0.3465 | 0.9495 |
| C | 0.348 | 2420 | 0.3176 | 1.096 |
| 合计 | 1 | 7620 | 1 | — |
| 表2-2 各分部工程评分值和目前成本表 | |||||
| 功能项目 | 功能得分 | 目前成本/万元 | 功能项目 | 功能得分 | 目前成本/万元 |
| 基础工程 | 21 | 2201 | 装饰工程 | 28 | 3224 |
| 主体结构工程 | 35 | 3669 | 水电安装工程 | 32 | 2835 |
| 表2-6 各功能项目改进计算表 | |||||
| 功能项目 | 功能得分 | 功能指数 | 目前成本/万元 | 目标成本/万元 | 成本降低期望值/万元 |
| 基础工程 | 21 | 0.181 | 2201 | 1810 | 391 |
| 主体结构工程 | 35 | 0.302 | 3669 | 3020 | 649 |
| 装饰工程 | 28 | 0.241 | 3224 | 2410 | 814 |
| 水电安装工程 | 32 | 0.276 | 2835 | 2760 | 75 |
| 合计 | 116 | 1.000 | 11929 | 10000 | 1929 |