选择题
75.
______ is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
A、
Analogous estimating
B、
parametric estimating
C、
Three-Point estimating
D、
Bottom estimating
【正确答案】
A
【答案解析】