单选题
An appropriate sequence for risk management activities is______.
A、
identify risks,perform qualitative risk analysis,perform quantitative risk analysis,plan risk responses
B、
identify risks,risk assessment。and risk planning
C、
identify risks,risk mitigation,and risk management
D、
identify risks,risk elimination,and risk mitigation
【正确答案】
A
【答案解析】
[解析] 风险管理活动适当的顺序是______。 A) 识别风险、定性分析、定量分析、规划应对 B) 识别风险、风险评估、风险规划 C) 识别风险、风险缓解、风险管理 D) 识别风险、风险排除、风险缓解
提交答案